The Prime Minister, Phạm Minh Chính, has mandated a faster pace for crucial national transportation projects in 2025, given the dwindling time remaining. Numerous road, rail, airport, and related infrastructure projects are slated for completion or commencement in the near future.
Target: 3,000 km of Expressway and 1,000 km of Coastal Roads
In a conclusion to the 16th meeting of the State Steering Committee for important national projects and key transportation projects, Prime Minister Phạm Minh Chính emphasized the critical importance of completing 3,000 km of expressways and 1,000 km of coastal roads by 2025. With just under ten months remaining in the year, substantial efforts are required from ministries, agencies, and local governments.
Accelerating Land Acquisition and Rail Project Approvals
Regarding rail projects, the Prime Minister urged localities with high-speed rail projects on the North-South route, and the Lào Cai – Hanoi – Hải Phòng rail project, to swiftly coordinate with the Ministry of Construction for land acquisition and resettlement project approvals to maintain project timelines. This crucial step will facilitate the implementation of these key rail lines.
Railway study for HCM City – Cần Giờ Metro and Long Thành Airport connection – 1
Developing the Railway Industry and Accelerating Urban Rail Projects
The Prime Minister directed the development of a Railway Industry Development Plan, encompassing research and proposals for Vietnam Railways Corporation and domestic enterprises to participate in adopting and transferring railway technology. The plan is to be completed by June 2025.
Specifically, Ho Chi Minh City is tasked with promptly studying and implementing the HCM City – Cần Giờ metro and the HCM City – Long Thành International Airport rail links. Investor and contractor proposals must be submitted by April.
Second Runway for Long Thành International Airport
For the Long Thành International Airport development project and connecting infrastructure, the Prime Minister instructed ACV to review procedures to begin construction of the second runway immediately in March. This is a crucial step for ensuring the future capacity of the airport.
Allocating Funds for Key Projects
Ministries, agencies, and localities must expeditiously allocate and detail the 2025 funding plans by March 15. The Ministry of Finance will reclaim unallocated funds to support key projects, accelerating progress.
Addressing Funding Issues for Projects
The Ministry of Finance was tasked with reviewing and balancing central government funding for Hà Giang, Tuyên Quang, and Đồng Tháp to ensure sufficient funds for the Tuyên Quang – Hà Giang and An Hữu – Cao Lãnh projects in 2025. Lạng Sơn Province is required to review and determine adjustments to increase state participation in the Đồng Đăng – Trà Lĩnh project.
Assessment and Adjustment of Other Infrastructure Projects
Assessment of the pre-feasibility study report for the Ho Chi Minh City Ring Road 4, adjustment of the Biên Hòa – Vũng Tàu project, assessment of the feasibility study reports for the Gia Nghĩa – Chơn Thành, Tân Phú – Bảo Lộc, Bảo Lộc – Liên Khương projects (Lâm Đồng Province), and the Ho Chi Minh City – Mộc Bài project (Tây Ninh Province) must be completed on schedule. Thái Bình and Hà Nội provinces are also asked to expedite the bidding process and commence expressway projects in April and May.
Strengthening Land Acquisition Efforts
The Prime Minister urged localities to mobilize the entire political system to acquire land for projects, adhering to commitment timelines to prevent delays.
Conclusion
These directives aim to ensure the completion of crucial transportation projects in 2025, contributing to comprehensive economic and social development and improving the lives of citizens. Close collaboration among ministries, agencies, and localities, coupled with a strong commitment to assigned tasks, is crucial for achieving these goals.