New Phong Chau Bridge Takes Shape After 5 Months of Construction

Nghiên cứu chính sách ưu đãi visa cho các tỷ phú, nghệ sĩ nổi tiếng

The new Phong Chau Bridge (Phu Tho Province) is under construction, linking Phuong Nguyen commune (Lam Thao District) to Van Xuan commune (Tam Nong District). Construction commenced in December 2024.

Previously, Typhoon Yagi on September 9, 2024, caused the collapse of two spans of the original Phong Chau Bridge over the Hong River, resulting in the disappearance of 8 people. To date, the bodies of 4 victims have been recovered.

The incident disrupted transportation between Lam Thao and Tam Nong districts, forcing residents to take significantly longer detours of 40-50 kilometers.

A temporary pontoon bridge was installed by the 249th Regiment, but fluctuating Hong River water levels frequently forced its closure. Traffic congestion was a recurring problem for commuters.

On December 21, 2024, the new bridge construction project began. The project, costing over 635 billion VND, is overseen by the Thang Long Project Management Board and executed by the Truong Son General Construction Corporation (Ministry of National Defence).

Our reporter observed the bridge construction site in mid-April, noting the intense activity of workers and numerous machinery and barges. The bridge’s initial structure is clearly visible after five months of construction.

Construction near the Hong River in Tam Nong District shows a major support pillar being framed and poured with concrete.

Construction in the river presented challenges, necessitating the use of numerous barges and cranes.

At the Lam Thao side of the construction site, the old bridge section (from pier T4 to pier T5) has been completely dismantled, and new piers are under construction.

Current low water levels expose the riverbed, allowing pier T5 to become more visible after days of construction.

The new bridge is expected to be approximately 652 meters long. This includes 383 meters of bridge span and connecting roads of 113 meters on the Lam Thao side and 155 meters on the Tam Nong side.

Many parts of the project are progressing ahead of schedule, with the bridge piers taking shape.

Piers T1 and T2 are now complete after five months of work and are ready for the installation of the bridge beams.

The completed Phong Chau Bridge will have a width of 20.5 meters, including 4 lanes for motor vehicles and 2 lanes for other vehicles. It is anticipated that the first bridge beams will be placed between piers T1 and T2 in mid-April.

The most challenging aspects of construction – piling, concrete pouring for piers T4 and T5 – are largely completed before the April high water season.

With this progress, project managers aim for the bridge to be completed in time for National Day (September 2nd). The bridge is expected to open before December this year.

Leave a Reply

Your email address will not be published. Required fields are marked *

New Phong Chau Bridge Takes Shape After 5 Months of Construction

U22 Việt Nam công bố danh sách, HLV Kim Sang Sik vắng mặt

The new Phong Chau Bridge (Phu Tho Province) is being rebuilt, connecting Phuong Nguyen Commune (Lam Thao District) to Van Xuan Commune (Tam Nong District).

Previously, the Phong Chau Bridge, spanning the Red River, collapsed in two sections during Typhoon Yagi on September 9, 2024, leading to the disappearance of eight people. Four victims have since been recovered.

This incident severed transportation links between Lam Thao and Tam Nong districts, making travel for residents very difficult, requiring detours of 40-50 km.

To mitigate this, the 249th Brigade installed a temporary pontoon bridge, but its frequent closure due to the Red River’s fluctuating water levels caused traffic congestion.

On December 21, 2024, construction began on the new Phong Chau Bridge project. The project, costing over 635 billion VND, is led by the Thang Long Project Management Board and executed by the Truong Son General Construction Corporation (Ministry of National Defence).

A Dân trí reporter observed the construction site in mid-April, witnessing workers diligently using many machines and barges. The first form of the new Phong Chau Bridge is emerging after 5 months of construction.

A key pier on the Red River side of Tam Nong district is being constructed and poured with concrete.

Construction amidst the river presents challenges, requiring the contractor to use numerous barges and cranes.

On the Lam Thao district side, the old Phong Chau Bridge section (from pier T4 to T5) has been completely dismantled, and new piers are rapidly being constructed.

Currently, the Red River water level is low, revealing some riverbed sandbars, and pier T5 is emerging after several days of construction.

The new Phong Chau Bridge is designed with a length of approximately 652 meters. This includes a bridge span of about 383 meters (measured to the end abutment), and approach roads of 113 meters on the Lam Thao side and 155 meters on the Tam Nong side.

Many sections are ahead of schedule, and the new bridge piers are taking shape.

Piers T1 and T2 are complete, showcasing their form after about 5 months of construction, and are ready for the bridge deck installation.

The main bridge has three continuous spans, constructed using a balanced falsework method. The approach section on the Lam Thao side comprises three approach spans, two beam spans. The abutments and piers are reinforced concrete, with drilled-pile foundations.

Dozens of beams are complete within the Lam Thao side construction area, awaiting placement on the finished piers.

The completed new Phong Chau Bridge will have a width of 20.5 meters, accommodating four lanes of motor vehicles and two lanes for other traffic. It’s anticipated that the first beams will be installed to connect piers T1 and T2 in mid-April.

Currently, the most challenging tasks, such as drilling piles, pouring concrete for the bases and bodies of piers T4 and T5 in the river, are largely completed before the April high water season.

With this progress, the project management board and the contractor aim to complete the bridge in time for National Day (September 2nd). The bridge is expected to open before December this year.